Merritt Parkway Projects

Logo
PROJECT PROGRESS
Project No. 102-0368

Recently completed work on this project includes:

  • Median box out for curb and gutter and median barrier
  • Installation of MP concrete curb
  • Installation of Two tube retrofit
  • Reset catch basin (Phase 1)
  • Paving Northbound (Phase 2)

Work in Progress:

  • Right shoulder installation of topsoil, seed and plantings
  • Full depth pavement reconstruction under bridge overpasses
  • Bridge concrete sounding for Class ‘S’ Historic Concrete Repairs
  • Stage 3 wedge course paving
  • Stage 4 median excavation and installation of drainage and MP guiderail at the north end of the project

 

Anticipated Work:

  • Median barrier excavation, boxout and barrier installation at West Rocks Road
  • Complete the final 2”lift of PMA S0.5 wearing surface between Grumman Avenue and West Rocks Road
  • Complete Merritt Parkway median curbing closure pours at the median barrier tie-ins
  • Merritt Parkway median guiderail installation
  • Install epoxy pavement markings in final configuration in advance of winter.
  • Continue installation of plantings and mulch in the median.

This Project is currently scheduled for completion on December 30, 2022. 

 

 

Project No.102-0296 

Recently completed work on this project includes:

  • Full depth pavement reconstruction southbound at Marvin Ridge Road and Comstock Hill Avenue and northbound at Comstock Hill Ave.
  • Tree Clearing southbound
  • Cleaning of existing drainage northbound and southbound

Work in Progress:

  • Milling and paving northbound White Oak Shade to Exit 40A Main Avenue
  • Full depth pavement reconstruction southbound at Marvin Ridge Road and White Oak Shade overpasses
  • Partial depth pavement repairs southbound/northbound – Nighttime
  • Clearing of hazardous trees and vegetation southbound – Nighttime
  • Removal of invasive vegetation northbound and southbound

Anticipated Work:

  • Milling and paving southbound Exit 40A Main Avenue to Exit 37 South Avenue
  • Milling and paving northbound Exit 37 at South Avenue to White Oak Shade overpass

This Project is currently scheduled for completion on October 31, 2024. 

Progress Photos

October / November 2022

July / September 2022

April / May 2022

February / March 2022

January 2022

December 2021

November 2021

October 2021

September 2021